PVDF tensile canopy · West Bank, Palestine · 2025
Palestine Sport Village grandstand canopies
PVDF tensile canopy · grandstand
Seven bays, two cantilever depths
Seven tensile PVDF canopy bays over two wings: 2,700 m² of membrane on 89 t of galvanised steel, cantilevered 12 / 25 m.
- Analysis and drawings first Design loads: snow 1.2 kPa, wind 140 km/h.
- Feasibility and technical development from the client's concept sketch.
- Architectural scheme and cast-in embedment coordinated with the concrete grandstand.
- Local approval package prepared with the client.
- Tekla model confirmed before production The Tekla model was confirmed and the seven bays went into production that month.
- Model adjusted to the as-built survey of the grandstand to tighten site fit.
- Fabrication Shop work only where it could be controlled; the site saw the minimum number of welds.
- Frame: CNC cutting and shop welding; only necessary welding on site.
- Fabric: Cutting and high-frequency welded in the shop — 1,300 g/m² PVDF, 10% translucency, 200 kN/m, flame retardant to EN 13501-1 B-s1, d0.
- Three shipments Loaded in May and June, shipped from GZ, CN to Ashdod, cleared with the client's broker.
- Client crew installed Erection started 21 July with our engineer's timely assistance; the municipality took handover on 3 October 2025.
Our scope
Structural design, shop drawings, fabrication, shipment, and remote technical support while the client's crew installed.
By others
Site installation and erection plant, the concrete grandstand structure, foundations and the rest of the sports village. Installation was carried out by the client's team.
Aerial view after handover
Seven canopies over two wings, the full-size pitch, and the courts behind it. Filmed by the main contractor.
Have a similar structure to deliver?
Share your drawings, specifications and project location. We'll review the structural requirements, fabrication approach, shipping configuration and key technical risks.